Scrum
Mental model
Section titled “Mental model”Scrum is not a way of building software — it is a way of finding out, every few weeks, whether what you are building is the right thing. The framework is “purposefully incomplete”: it defines a team, a cadence, and three artifacts, and says nothing about how you estimate, design, or ship. Everything in it serves empiricism — make the work visible, inspect it against a goal, adapt. A ceremony that changes no decision is not Scrum, whatever the calendar invite says.
Empiricism: the three pillars
Section titled “Empiricism: the three pillars”| Pillar | Demands | Without it |
|---|---|---|
| Transparency | Work visible to all | Inspection misleads |
| Inspection | Progress checked often | Nothing to adapt to |
| Adaptation | Adjust as soon as you learn | Inspection is pointless |
Scrum is founded on empiricism and lean thinking: knowledge comes from experience, decisions from what is observed. The pillars are a chain, not a menu — the guide is blunt that “inspection without transparency is misleading and wasteful” and that inspection without adaptation “is considered pointless”. The events exist to force that chain to complete on a fixed cadence, and the five values — Commitment, Focus, Openness, Respect, Courage — are what make people willing to be transparent at all.
Transparency -> makes inspection possibleInspection -> makes adaptation possibleAdaptation -> changes the next SprintThe Scrum Team
Section titled “The Scrum Team”| Accountability | Accountable for |
|---|---|
| Developers | The Increment and its quality |
| Product Owner | Product value; the Product Backlog |
| Scrum Master | Scrum itself; team effectiveness |
One team, typically 10 or fewer people, with no sub-teams and no hierarchy inside it. It is cross-functional — it holds every skill needed to create value each Sprint — and self-managing, deciding internally who does what, when, and how. The Product Owner is one person, not a committee, and for the accountability to mean anything “the entire organization must respect their decisions”.
1 Product Owner one person, not a committee1 Scrum Master serves; does not assign workDevelopers anyone doing the workGotcha: The Scrum Master is not a project manager. Nothing in Scrum gives anyone authority to assign work to a Developer — the Developers select and plan it themselves, and “no one else tells them how to turn Product Backlog items into Increments of value”.
Artifacts and commitments
Section titled “Artifacts and commitments”| Artifact | Commitment | Answers |
|---|---|---|
| Product Backlog | Product Goal | Where the product goes |
| Sprint Backlog | Sprint Goal | Why this Sprint matters |
| Increment | Definition of Done | Whether it is real |
Every artifact carries a commitment, so that inspecting it means something. The Product Backlog is an emergent, ordered list and “the single source of work undertaken by the Scrum Team”. The Sprint Backlog is the Sprint Goal (why), the selected items (what), and the plan (how) — “a plan by and for the Developers”, updated throughout the Sprint as more is learned. Refinement is an ongoing activity rather than an event, and the Developers who will do the work do the sizing.
Product Goal Product Backlog ordered, emergent Sprint Backlog goal + items + plan Increment meets Definition of DoneDefinition of Done
Section titled “Definition of Done”| Situation | Consequence |
|---|---|
| Item meets the DoD | An Increment is born |
| Item does not | Back to the Product Backlog |
| Organization sets one | Every team follows it as a minimum |
| It does not | The team must create one |
| Several teams, one product | They share a single DoD |
The Definition of Done is “a formal description of the state of the Increment when it meets the quality measures required for the product” — your quality bar, written down, applied to every item. It is what makes a Sprint’s output honestly inspectable: work that misses it “cannot be released or even presented at the Sprint Review”. Developers are required to conform to it.
Done - Checkout service (example) Reviewed by another Developer Unit + integration tests green in CI Logs, metrics and an alert in place On staging, no open P1 defectsWarning: “Done except testing” is not Done. It does not enter the Increment and it is not shown at the Sprint Review — it returns to the Product Backlog. A team that ships around its own Definition of Done has deleted the only quality check the framework has.
The Sprint
Section titled “The Sprint”| Aspect | Rule |
|---|---|
| Length | Fixed, one month or less |
| Next Sprint | Starts immediately after the last |
| Sprint Goal | No change that would endanger it |
| Quality | Does not decrease |
| Scope | Renegotiable with the Product Owner |
| Cancellation | Only the Product Owner may cancel |
The Sprint is the container for every other event and the unit of inspection — “Sprints are the heartbeat of Scrum, where ideas are turned into value”. Fixed length is what turns it into a measurement; a Sprint extended by three days to finish the work measures nothing. Shorter Sprints generate more learning cycles and cap the cost of being wrong, so one month is a ceiling, not a target. A Sprint may be cancelled only when its Sprint Goal becomes obsolete.
| Sprint 14 | Sprint 15 | Sprint 16 | no gap, no hardening week, no Sprint 0Gotcha: “Nothing changes during a Sprint” is a myth. Scope may be clarified and renegotiated with the Product Owner as more is learned. What is protected is the Sprint Goal, not the ticket list.
Sprint Planning
Section titled “Sprint Planning”| Topic | Question | Who decides |
|---|---|---|
| Why | Why is this Sprint valuable? | Whole Scrum Team |
| What | What can be Done this Sprint? | Developers, with the PO |
| How | How will the work get done? | Developers alone |
Timeboxed to a maximum of eight hours for a one-month Sprint, and usually shorter for shorter Sprints. The Sprint Goal must be finalized before Planning ends — without one there is no objective to protect and nothing to renegotiate scope against, so the Sprint decays into a list of tickets. Decomposing selected items into work of a day or less is a common tactic the guide mentions, not a rule.
Weak: "Deliver PROJ-412, 417 and 419."Good: "A returning customer can check out without re-entering card details."Daily Scrum
Section titled “Daily Scrum”| Fact | Value |
|---|---|
| Timebox | 15 minutes |
| For | The Developers |
| When | Same time and place, every working day |
| Structure | Whatever the Developers choose |
| Purpose | Progress toward the Sprint Goal |
The event exists to produce “an actionable plan for the next day of work”. The Product Owner and Scrum Master take part only as Developers — that is, when they are actively working on Sprint Backlog items. It is also not the only time Developers replan; they meet throughout the day for more detailed discussions as needed.
Not: round-robin status for a managerYes: will we hit the Sprint Goal, and what changes today if we won't?Gotcha: The three questions (“what did I do yesterday…”) were removed in the 2020 Guide. A Daily Scrum run as a status report to the Scrum Master inverts the event: it is the Developers’ own replanning meeting, and nobody in it is reporting to anybody.
Sprint Review and Retrospective
Section titled “Sprint Review and Retrospective”| Event | Timebox | Purpose |
|---|---|---|
| Sprint Review | 4 hours | Inspect outcome, decide next |
| Sprint Retrospective | 3 hours | Raise quality, effectiveness |
Both timeboxes are maximums for a one-month Sprint and are usually shorter for shorter Sprints. The Review puts the Scrum Team and its stakeholders over the Increment together, and the Product Backlog may be adjusted on the spot — it “is a working session and the Scrum Team should avoid limiting it to a presentation”. The Retrospective inspects individuals, interactions, processes, tools and the Definition of Done, and concludes the Sprint; the most impactful improvements may go straight into the next Sprint Backlog.
Review: team + stakeholders -> what nextRetro: the Scrum Team -> how we workGotcha: The Sprint Review is not a release gate. An Increment may be delivered to stakeholders before the Sprint ends — holding finished work back for a demo is a delay you chose, not one Scrum imposed.
What Scrum does not define
Section titled “What Scrum does not define”| Not in the guide | What it actually is |
|---|---|
| Story points, velocity | An estimation practice |
| Backlog grooming | Older name for refinement |
| Sprint zero, hardening | Every Sprint must be Done |
| The three daily questions | Dropped in 2020 |
| Burn-down charts | One forecasting option |
| A specific tool or board | Scrum requires no tool |
Of the terms above only burn-downs appears in the guide at all, named once beside burn-ups and cumulative flows with the caveat that such practices “do not replace the importance of empiricism”. Treat the rest as local choices you must justify on their own merits; they inherit no authority from Scrum. The framework is small on purpose — it “wraps around existing practices or renders them unnecessary”.
Warning: The reverse holds too. Dropping a part is not a lighter Scrum: “While implementing only parts of Scrum is possible, the result is not Scrum.” Name what you actually run, and own the trade-off instead of borrowing the word.